Sunday 18 September 2011


The majority of the basic studwork is now completed.  On the main landing wall we have the ductwork for the MVHR ventilation system running.  The idea for this wall is to build it out (to make it a thick wall) and in the centre there is going to be a recessed bookshelf.  This weekend we started framing out the bookshelf and building the studwork on the other side of the ductwork.