Thursday, 28 April 2011

Day 382













































Cladding is about half way along south elevation now.

Tuesday, 26 April 2011

Day 380 - west doors glazed


























The sliding doors are now complete on the west elevation.  We now just need to glaze the south sliding doors.












































...and the glass goes into the triple sliding doors!

Friday, 22 April 2011

Day 376 -sliding doors in triple track


























Sliding doors fitted in the triple track today... just the glazing to go.

Wednesday, 20 April 2011

Day 374













































Cladding progresses on the south elevation...

Tuesday, 19 April 2011

Day 373


























The pair of sliding doors were fitted into the frames on south elevation today... just the glass to go now!

Sunday, 17 April 2011

Day 371


























We started putting in the sheeps wool insulation between the battens.  This is the final bit of the insulation in the roof, bringing the total depth to 250mm.












































We also built the frame around the twin-walled chimney.  This will be enclosed with magnesium board.  It is important to keep all combustible materials at least 50mm from the chimney, and to maintain a 50mm air gap around the chimney.  This boxing will achieve both these things.  When we put the magnesium board on, we will need to ensure that we put in air vents to allow any heat to dissipate.

Insulation and rafters in the roof also must be kept 50mm away from the chimney.

Saturday, 16 April 2011

Day 370

We completed the battens to the underside of the rafters today!

Sunday, 10 April 2011

Day 361


























...and put more sheeps wool in.

























This weekend we fixed more battens to the underside of the rafters...

Wednesday, 6 April 2011

Day 357 - More sheeps wool


























More sheeps wool arrives for insulating the roof.

Tuesday, 5 April 2011

Day 356 - Electricity supply put in


























New electricity supply put in...

Monday, 4 April 2011

Day 353-355


























The last 3 days we have been continuing to fix the battens on the underside of the rafters.  These will increase the depth of insulation by an extra 100mm (4 inches).

Thursday, 31 March 2011

Day 351 - Frames for the sliding doors fitted













































The aluminum frame sitting behind the cedar cladding.  It is a triple track, which allows all three of the doors to slide, two one way and one the other.

























The frames for the sliding doors were fitted today.  These are bedded on a lime mortar (NHL5, mix 3:1).

When we ordered the windows we asked for them to be 12.5mm smaller than the structural opening on all sides, so the windows were overall 25mm narrower and 25mm shorter than the hole they were fitting into.  When we ordered the doors we were advised that 5mm on all sides, so 10mm overall was sufficient.  However, while the frames do fit within the opening, the gaps on some of the sides are now very small, once the frames have been squared up.  This is going to make it much harder to adequately seal the gaps against weather and achieve a satisfactory airtightness and thermal performance.

Wednesday, 30 March 2011

Day 350


























What will be the walls of the utility room have been covered with smart ply, to enable mechanical and electrical services to be easily fixed to them.

Tuesday, 29 March 2011

Day 349 - Internal studwork begun


























Internal partitions to the utility room were begun today.

























Cedar lining to the rest of the windows complete...