Sunday, 31 October 2010

Day 201 - Straw bales complete


























Last straw bale fitted!

Saturday, 30 October 2010

Day 200


























... on the plywood between the ground and first floor bales.  We are using this to help the clay render adhere to the timber.

























Expanded metal lath cut ready to fit...
































An aerial photo recently sold to us, taken on 9th August.  A good overview of the site, bungalow and straw house (and strawbale stack)!

Friday, 29 October 2010

Day 199 - Steel bars fitted to roof


























The roof sheet will be fitted directly to the galvanised steel bars.












































Ahsgrid bars and brackets fitted to one side of the roof.

Wednesday, 27 October 2010

Day 197













































Clay slip coat completed on 3/4 of the first floor.

























More straw progressed on the east gable.

























Viewed from the ground.












































Housed in aluminium













































The soil stack venting through the roof...

Tuesday, 26 October 2010

Day 196













































... and the second...

Monday, 25 October 2010

Day 195













































Our first attempt at triangular bales!

Sunday, 24 October 2010

Day 194


























First sheepswool insulation fitted between gable rafters.












































Blocks for the steel bar and brackets decorated.












































Top course of bales complete, leaving only the gables to be done.

Saturday, 23 October 2010

Day 193


























Top course of bales almost complete on south elevation.  All the third course of bales now compressed with the permanent white straps fitted.

Friday, 22 October 2010

Day 192


























Top course of compressed bales completed about half way along the south elevation.

Wednesday, 20 October 2010

Day 190 - First bars fitted on the roof


























Blocks beyond ply roof deck fitted along with the first steel bars and brackets.  The corrugated roof sheet will be fixed to these bars.

Tuesday, 19 October 2010

Day 189


























Starting to compress and fit the top course of bales on the first floor.