Thursday, 30 September 2010
Day 170 - GF straw complete... again
Last ground floor straw wall complete (for the second time!)
... the completed window linings on the first floor.
First floor window linings complete in the bedrooms...
Our home made straw and tarpaulin pool filled with milled clay, and soaked in water.
Tuesday, 28 September 2010
Day 168
GF straw almost complete... for the second time!
Lime and hemp completed round to the stair window.
Sunday, 26 September 2010
Day 166
Hemp and lime complete from front door on east elevation, all along south elevation and half way along west elevation.
The north west corner complete.
Top course of bales complete on the north wall.
Saturday, 25 September 2010
Day 165
The first bales put in on the first floor under the windows, ready for the window linings to be begun.
Top course of small bales begun on the north wall.
North wall re-instated!
More straw taken out of the north elevation, most of it was in fact dry but better to be safe than sorry!
Friday, 24 September 2010
Day 164
Straw completed on south elevation and south west corner.
Blocks fitted to each rafter for fixing the gutter to.
Head section to both sets of sliding doors completed.
Restraint straps fitted on the west gable.
Thursday, 23 September 2010
Day 163 - solar panels fitted
Solar panels fitted on the south roof.
Monday, 20 September 2010
Day 161
Hemp and lime completed under the FF window in the east elevation, and about 1/2 of the east elevation complete.
Straw is now re-instated in the south wall - except the top course of small bales.