Wednesday, 20 April 2011

Day 374













































Cladding progresses on the south elevation...

Tuesday, 19 April 2011

Day 373


























The pair of sliding doors were fitted into the frames on south elevation today... just the glass to go now!

Sunday, 17 April 2011

Day 371


























We started putting in the sheeps wool insulation between the battens.  This is the final bit of the insulation in the roof, bringing the total depth to 250mm.












































We also built the frame around the twin-walled chimney.  This will be enclosed with magnesium board.  It is important to keep all combustible materials at least 50mm from the chimney, and to maintain a 50mm air gap around the chimney.  This boxing will achieve both these things.  When we put the magnesium board on, we will need to ensure that we put in air vents to allow any heat to dissipate.

Insulation and rafters in the roof also must be kept 50mm away from the chimney.

Saturday, 16 April 2011

Day 370

We completed the battens to the underside of the rafters today!

Sunday, 10 April 2011

Day 361


























...and put more sheeps wool in.

























This weekend we fixed more battens to the underside of the rafters...

Wednesday, 6 April 2011

Day 357 - More sheeps wool


























More sheeps wool arrives for insulating the roof.

Tuesday, 5 April 2011

Day 356 - Electricity supply put in


























New electricity supply put in...

Monday, 4 April 2011

Day 353-355


























The last 3 days we have been continuing to fix the battens on the underside of the rafters.  These will increase the depth of insulation by an extra 100mm (4 inches).

Thursday, 31 March 2011

Day 351 - Frames for the sliding doors fitted













































The aluminum frame sitting behind the cedar cladding.  It is a triple track, which allows all three of the doors to slide, two one way and one the other.

























The frames for the sliding doors were fitted today.  These are bedded on a lime mortar (NHL5, mix 3:1).

When we ordered the windows we asked for them to be 12.5mm smaller than the structural opening on all sides, so the windows were overall 25mm narrower and 25mm shorter than the hole they were fitting into.  When we ordered the doors we were advised that 5mm on all sides, so 10mm overall was sufficient.  However, while the frames do fit within the opening, the gaps on some of the sides are now very small, once the frames have been squared up.  This is going to make it much harder to adequately seal the gaps against weather and achieve a satisfactory airtightness and thermal performance.

Wednesday, 30 March 2011

Day 350


























What will be the walls of the utility room have been covered with smart ply, to enable mechanical and electrical services to be easily fixed to them.

Tuesday, 29 March 2011

Day 349 - Internal studwork begun


























Internal partitions to the utility room were begun today.

























Cedar lining to the rest of the windows complete...

Monday, 28 March 2011

Day 348













































Cladding continues on south elevation...

Sunday, 27 March 2011

Day 347 - sheeps wool roof insulation begun


























The battens fixed below the rafters, and the sheeps wool in place.  There will be more insulation running between the battens.

























We started battening the underside of the roof yesterday and putting in the sheeps wool insulation today. The wool is soft and smells very 'sheepy'!.

Friday, 25 March 2011

Day 345 - cladding complete on north elevation


























The completed north elevation.

























Street view of the completed elevation...












































Cladding on the last elevation started...

























Cladding on north elevation complete!  (and downpipe half put up)

Thursday, 24 March 2011

Day 344


























North elevation almost complete...

Wednesday, 23 March 2011

Day 343

Tuesday, 22 March 2011

Day 342

Monday, 21 March 2011

Day 341

Sunday, 20 March 2011

Day 340 - Hemp and lime insulation complete



























We finished off the hemp and lime insulation to the eaves void, above the straw bales.

Saturday, 19 March 2011

Day 339


























Second coat of plaster put on the utility room wall.  This is also the last coat on this wall as it will have timber studs in front of it lined with plywood.  This is because it is our mechanical plant wall and we needed to be able to fix to it easily.

Friday, 18 March 2011

Day 338


























... and another.  It almost looks like we have finished from here!

























The street view...












































The cladding in the brief late afternoon sun.

























Half the cladding complete on north-west elevation!

Thursday, 17 March 2011

Day 337













































Cladding has now passed the stair window...

Tuesday, 15 March 2011

Day 335


























Battening begun to south elevation.












































Cladding progressing...

Monday, 14 March 2011

Day 334 - Cladding to north elevation begun


























Battens completed to north elevation, and cladding begun...

Saturday, 12 March 2011

Day 332 - Climbing plants planted













































The front elevation (north-east) and north-west elevation are intentionally quite blank.  This is to prevent excessive heat loss through openings / glazing facing north, which receive little sun / heat gains.  The majority of windows are designed to face south instead.

To add interest to the front and north elevations we are planning to grow climbing plants up them, so in time they become 'green walls'.  As the cladding is now complete on the front elevation we decided to give the climbing plants a head start (as they will take time to establish), and plant the 'Parthenocissus Henryana' (virginia creeper).

Thursday, 10 March 2011

Day 330


























Battening started on north elevation...












































Cladding finished on the front elevation!

Wednesday, 9 March 2011

Day 329

So close...

Tuesday, 8 March 2011

Day 328













































Getting closer...

Monday, 7 March 2011

Day 327 - Cladding continues













































Putting up the cladding on the front resumed on Friday.  Nearly half way now...  The 'hit and miss' boarding over the bathroom window is also complete.

Sunday, 27 February 2011

Day 319 - More clay!


























More clay rendering this weekend.  Yesterday rained again, which is becoming the norm for Saturdays!  Good progress today, we have now completed stripping off the frost damaged render and just need to patch in some cracks which have appeared in the render as it is drying.

Friday, 25 February 2011

Day 317 - Cladding the front elevation underway













































Cladding begun on the front elevation yesterday.

Thursday, 17 February 2011

Day 309 - Guttering complete


























Guttering complete on both sides.  The downpipes are yet to be fitted, once the cladding has been fitted.

Wednesday, 16 February 2011

Day 307


























Guttering erected on 3/4 of the other side.

Tuesday, 15 February 2011

Day 306 - Guttering begun













































...one side virtually complete

























Putting up the aluminium guttering started today...

Sunday, 13 February 2011

Day 304

More external rendering today.  We finished the south elevation yesterday, and today we got from the road to the stair window on the north elevation.

We think the clay on the east (road) elevation has held up well under the poor winter weather conditions and does not need to be replaced.  We will do some final inspections next weekend, but our fingers are crossed!

Saturday, 12 February 2011

Day 303 - external clay finished on south elevation













































Where we had to knock the render off, we took it back to the clay slip coat.

We have now finished rendering the south elevation, hopefully it will have a chance to dry this time!












































Another example of where the frost has blown off part of the previous coat of render.  Whilst some of the render is still on the wall, it has lost its key to the render below.  It was sole destroying but we had to knock a lot of it off, particularly at high level.  If we hadn't knocked it off, it would have been pulled off by the application of the next coat of render.