Tuesday, 21 December 2010

Day 250 - Scaffolding struck













































The front elevation












































The roof overhang on the west elevation.

























The west elevation post scaffolding.












































The frozen scaffolding ready to come down...

Sunday, 19 December 2010

Day 248


























We need to cast a limecrete sill under each of the sets of sliding doors, and the quicker we can get this done the sooner we can order the sliding doors.  The freezing weather has not been very helpful, as lime likes a minimum external temperature of 3degrees C.

To try and get round this we had an idea that we could build a straw bale tunnel over each of the sills and put an electric greenhouse heater in each one, with the aim of keeping the internal temperature above 3deg C.  We constructed one of the tunnels to see what sort of temperature we would be able to maintain within the tunnel, to see if the idea would work...

...we found that the temperature was on average about 4 degrees higher within the tunnel than the external air temperature (there were a few gaps between the bales we couldn't do much about).  This was simply not enough when the external air temperature is between -5 and -10, as it is at the moment!  So we will have to wait until there is a break in the weather before casting the sills.

Friday, 17 December 2010

Day 246 - the roof is finally complete!













































... the last roof sheets were fitted!
The temperatures are still very low here but as the scaffolding is due to come down next week we were desperate to get the roof finished.  So we dragged up hot water and towels to thaw the ice on the roof and finally... 

Sunday, 12 December 2010

Day 241 - clay disaster


























Some of the larger cracks and what we think are salts brought to the surface by the cold weather.

If anyone has experience of clay render they can share with us, we would be very interested to listen...

























More pictures of the frost damage to the render...












































The temperature was forecast to drop to +2 degrees last night, however when we got up this morning it was -3 degrees.  Significantly colder than forecast!  This was not good news.  The render we applied yesterday had frozen already, and the clay in the pit had frozen once again.  One area of render had fallen off, pictured above, so not the best start to the day!  We took the difficult decision not to do anymore rendering today and are questioning whether we leave the rendering until next Spring.

Saturday, 11 December 2010

Day 240 - the big rendering weekend!


























The weather forecast for this weekend was a break from the extremely cold weather so we planned a big rendering weekend, and called all hands on deck to help!  However, on Saturday morning we did a thorough inspection of the render and discovered some frost damage had occurred, particularly on the north-east elevation which has fronted a lot of the cold weather we have had recently.  The frost appears to have frozen the water in the wet render and expanded it, and then once thawed the clay has stayed expanded leaving it aerated like an aero bar.  The render has also not really dried in places and in others has lost its key.  The good thing we discovered about the clay was that this process was reversable and it could be returned to its original state.

We carried out some remedial work and decided we had nothing to loose by trying to get as much of the remaining high level rendering done (on the north and south elevations) before the scaffolding is struck in about a weeks time.

Thursday, 9 December 2010

Day 239


























2/3 of the ridge sheets are now fitted. We are nearly there with the roof!  ( I appologise for the night shot!)

Wednesday, 8 December 2010

Day 238













































Cladding battens set up on the east elevation.












































The replacement ridge sheets have arrived and...

... they fit!

Tuesday, 7 December 2010

Day 237













































Close up of the horizontal cladding around glazing on west elevation.

























Horizontal cedar boarding on the west gable is complete and looks really good!

Many thanks to our carpenters, Steve Jarvis & Sons, who have done a fantastic job in very cold conditions (some mornings it was -6 degrees!).  They have also put up the whole timber frame, done all the metal roofing and fitted all the windows.  Their attention to detail is amazing and they have been very enjoyable to work with.  Many thanks to you all.

Sunday, 5 December 2010

Day 235


























Another weekend when it has been too cold to progressing the clay rendering so...

More cold weather jobs... putting a 15 degree angle on the top edge of the cladding battens...

Friday, 3 December 2010

Day 233 - First cedar boards fitted


























The first boards...












































First cedar boards fitted on west gable around the first floor glazing (above the sliding doors).  These are the only horizontal boards, the rest of the cladding will be vertical.

Thursday, 2 December 2010

Day 232


























Balustrading fitted on the west gable in front of opening glazing (you won't see the fixings once the cedar cladding is fitted) and cedar lining around sliding doors fitted today.

Wednesday, 1 December 2010

Day 231


























Cladding battens fitted on the west gable.

Monday, 29 November 2010

Day 229













































Breather membrane and black battens fixed on west gable, ready for the cedar boards.

Sunday, 28 November 2010

Day 228 - cold weather jobs...













































The cold weather has hampered progress somewhat and has limited the amount we can do.  One of todays projects was making a temporary front door to keep the cold north wind out!

Friday, 26 November 2010

Day 226 - winter arrives early!


























We wanted to finish the clay rendering this weekend but it doesn't look like the weather will allow us to.

























The weather changes... the snow and ice has arrived early.

Monday, 22 November 2010

Day 222













































All roof sheets complete, except the ridge sheets.













































Second coat of clay render complete on the south elevation.

Saturday, 20 November 2010

Day 221


























... and second coat started on the south elevation.

























Second coat of render complete on the north elevation...

Friday, 19 November 2010

Day 220


























... the last bit to go... and then the ridge sheets to fit

























South side of the roof nearly complete...

Thursday, 18 November 2010

Day 219 - north side of the roof complete


























The completed north side of the roof...

























The roof overhang on the west elevation.

























Roof sheets complete on the north side of the roof.

Tuesday, 16 November 2010

Day 217


























Roof sheet progressing on the south side of the roof (the north side was too icy to continue with and didn't really thaw before it re froze!).

Sunday, 14 November 2010

Day 215 - clay render on front elevation complete













































Our weekends work - completing the clay render on the front elevation.

Friday, 12 November 2010

Day 213



























Yesterday was too windy to fit any aluminium sheets, today was boarder line.  Damn weather!!  We managed to finish off the cut sheets around the rooflight but it was too windy to fit any of the full length sheets.

Wednesday, 10 November 2010

Day 211 - Aluminium sheet begun


























The first day's progress...

























The complicated junction with the roof light flashings and roof sheet at the bottom of the roof light.

























Starting to go round the first roof light.












































What the view from the underside will be like...












































First aluminum roof sheet fitted.

Sunday, 7 November 2010

Day 208



























Render complete on west gable and 1/2 complete on east gable.

Saturday, 6 November 2010

Day 207 - clay render begun














































3/4 of the render complete on the west elevation.












































The first rendered panel...

























The clay render mixed up and ready to go.  Mix is 1:2:1 (clay slip: sand: chopped straw).

























Emptying out the chopped straw.

























We found a leaf collector a quicker to cut the straw (to go in the clay render) than the garden shredder.

























Street view

Monday, 1 November 2010

Day 202


























Bars and brackets fitted on the other side of the roof, along with insect mesh at eaves and gables.