Tuesday, 20 April 2010
Monday, 19 April 2010
Friday, 16 April 2010
Looks like this corner of the site may have previously been used as some sort of dumping ground. There is lots of rubble and general builders waste, which seems to have been buried and filled in. It makes the edges of the trenches very unstable, and prone to collapse. This will be challenging to blind with sand tomorrow!
Thursday, 15 April 2010
Wednesday, 14 April 2010
Tuesday, 13 April 2010
Day 2 surprises!
Surprise 2
A lump of concrete was discovered about 1meter below finished ground level. Again near the north boundary. It looks like it goes laterally across the trenches, so we shall see if it makes an appearance in the next trench when we get far enough along. We are not sure what it is, if we can lay the ground source pipe over it, or if we need to remove it first.
Day 2 progress is quite slow - probably managing to pull about 50 metres a day. So far about 3 out of 14 '300mm (foot) trenches' have been completed and one of the 1 metre wide lateral trenches. What we had originally considered as a 5 day job is looking like it is becoming more like 7 days. We were also met with two surprises today...
Day 2 reinforcements, in the form of a dumper!
Having decided yesterday that it was just not possible to stack the soil by the side of the trench we investigated possible places to put it. It was agreed this would be put at the back of the site over the proposed location of the new footprint. This leaves space at the front of the site, also on top of the proposed footprint, for the 34 cubic meters (about 60tonnes) of sand we need to blind the trenches and cover the pipe loop with!
Monday, 12 April 2010
In theory it sounded simple - one 400 metre loop of 40mm pipe, laid a minimum of 1000mm in the ground (we were advised to go for 1200mm) and at a min 1000mm centres, starting and ending at the heat pump. The drawing also looked simple but hid the logistical nightmare it was going to turn out to be!
We had ruled out backfilling the trenches as we went, because we needed to lay and pressure test the pipe before we covered it. So, our plan was to neatly stack the spoil from each trench to one side of the corresponding trench and work sequentially along the trenches (we had decided to ignore the problem of how we would gain access to the trenches to blind them with sand and lay the pipe once all the trenches had been dug!). To make life a bit easier we had increased the centres of the trenches to 1200mm, which was about the maximum we could easily accommodate on the site.
Tuesday, 2 February 2010
Monday, 4 January 2010
Subscribe to:
Posts (Atom)